Nov 17-22 Moving along

14 3

The framing was completed this week on the interior walls, the drop down ceilings (between the beams to hide the sprinklers, and plumbing and electrical rough in). The deck framing will begin next Monday and will be completed by 12/5. YAY!

Patrick and Jon built a beautiful exterior archway to support the exterior great room deck roof. They have two more to be built in the next few weeks that will be decorative for the interior of the great room. 

The windows are still being installed. The primary suite is complete, and another 6-8 windows in the house are already installed. With the exception of the windows/doors in the Great Room, all the remaining windows will be completed by the Friday after Thanksgiving. That’s SO exciting!

This week, the plumbers started to do their plumbing rough- in. All of the plumbing rough-in should be completed by 12/5. 

We ran the ditch for the electrical line from the panel to the mechanical room. (Thank you Darryl for digging the ditch!) The other trades are filling the mechanical room with their equipment too. It’s starting to come together. 

We were busy with meeting with the architect, the engineer and also the County inspector, to keep the project moving along. 

The front door has been completed in Montana and will be shipped to us ASAP!

We moved forward with the interior trim/door package order, and finalized the fireplace purchase for the great room and the primary suite. 

So grateful for this team that is making things happen!